Demolition of a two storey office building with additional soft strip and silte clearance.

Remove 50 no. external loading dock shelters, internal floor dock levelers, insulated doors, hot rolled steel work and associated
bollards.
Remove existing fire door sets and Armco barrier/ bollards.
Remove all the internal building fabric, fittings, fixings and redundant equipment between grid-Lines 1-3.A-H to facilitate the
new drive through side loading process, inclusive of the Armco barriers.
Remove the existing canopies and cladding (1,791 sqm) to the warehouse elevations.
Take down temporary storage structure (35x 26m).
Remove the existing elevated cubica system, remove the existing first floor walkway, offices and staircase to the warehouse.
Demolish and remove the 2 storey offices. Remove slab and foundations. All materials to be cleared of site.
Remove and dispose of all existing services.
Demolish the existing gate house.
Remove and dispose of metal palisade fencing 383m Remove and dispose Armco barrier around the gatehouse.