Brunswick Apartments, Southampton

Project Description

The next course of action was to install a Prokol Pure Poly- urea & Polyurethane liquid coating to the flat roof area, this system on completion provided our client with a 50 year warranty.

While the works were being carried out our team of seal- ant engineers, began sealing the external curtain wall win- dow system with mastic sealant, working on one drop at a time.

During the course of our works, it was identified that the entire building did not have any fire strategy in place and a majority of the fire stopping was either missing of totally non compliant, this also included the lack of fire stopping behind all door architraves. Initially we carried out a full photographic survey, which identified all areas that re- quired remedial action.

The planned re-instatement of the fire stopping took place, which required access to all apartments and communal areas. On completion a full photographic report was made available to the client, via an on line portal.

As previously mention various rooms had become unhabit- able, due to water damage. Redbridge carried out the re- furbishment of all damaged rooms, inclusive of laying new flooring and redecoration on completion.

Scope of work

• Installation of scaffolding and cradles
• Removal and replacement of new “Green Roof”
• Remove and re-install solar panels / install new inverter
• Install Prokol System to podium roof
• Remove existing mastic and re-seal all curtain wall glazing
• Replace missing rivets to curtain walling
• Supply and replace broken high level windows
• Carry out fire stopping survey of entire building
• Install and replace all fire stopping to third party accredited
standards
• Carry out the refurbishment of water damaged rooms, to include new flooring to various rooms and corridors.

Project Gallery

Key Achievements

During the course of the project, additional works were added, which ended up with the contract tripling in size.

Redbridge carried out all additional works to aid a smooth transition in completing the total project in a timely fashion and with the least disruption to the residents.