Redbridge Group

Newell Street

Project Description

The building to be demolished was situated on a very narrow street, which hindered the progress of the works, the local residents were all informed of the proposed works and kept informed of all processes.

Redbridge were employed as Principal Contractor for the project.

Scaffold was erected on the pavement to allow some of the works to be carried out by hand. The building was successfully demolished on time.

During the course of the works, Redbridge were instructed to carry out some additional works within a retained part of the building, these works included the removal of partition walls and ceilings and the disposal of loose furnishings within the building.

The additional works were completed and did not cause any adverse delays to the overall programme

Scope of work

Project Gallery

Key Achievements

Tags :

Share :